Opportunity timeline

PostedSep 14, 2026
DeadlineSep 30, 2026

In plain English

Fort Bend County Municipal Utility District No. 242 is seeking installation of water, sanitary sewer, storm sewer, and paving improvements for August Trails Section Four. The work includes about 3,533 linear feet of waterline, 2,977 linear feet of gravity sanitary sewer, 5,302 linear feet of storm sewer, and 10,207 square yards of reinforced concrete.

About this opportunity

Project scope shall include the installation of approximately 3,533 LF of 6"-12" PVC waterline; 2,977 LF of 8"-10" PVC gravity sanitary sewer; 5,302 LF of 24”-60” polypropylene pipe storm sewer; and 10,207 SY of 6” reinforced concrete. Sourced from CivCast, where plans, addenda, and bidding are managed.

Time remaining

Closes Sep 30, 2026

16Days
:
14Hours
:
46Min
:
16Sec

Related Opportunities

Bid details are gathered and summarized automatically. Please verify details at the original source.

Ref No.

BS-DACF34