Bid guide
How to bid on the US 19/SR 9 Bridge Replacement for Georgia DOT
What the agency is buying
The Georgia Department of Transportation (DOT) is looking for a construction manager/general contractor. This contractor will provide both preconstruction and construction services. The project involves replacing the US 19/SR 9 Bridge over CSX Railroad #639817J in Fulton County, Georgia.
The new bridge will follow the existing alignment, span the CSX tracks and the Atlanta Beltline trail, and meet current design standards. It will also be designed to accommodate a possible future track expansion beneath the structure.
Key dates and deadlines
This opportunity was published on July 02, 2026. The deadline for responses is September 04, 2026, at 11:00 AM ET. All submissions must be received by this time.
The contract will be awarded using a One-Phase Best Value selection method.
Who this opportunity suits
This solicitation is suitable for construction firms with experience in bridge replacement projects, particularly those involving railroad crossings and accommodating future infrastructure expansions. Firms with expertise in construction management and general contracting services for state transportation projects are encouraged to respond. The project is categorized under construction.
How to respond
To access the full solicitation documents and instructions on how to respond, you need to go to the Georgia Procurement Registry (GPR). The event number is PE-48401-RFQC-2027-000000610.
Viewing the posting and its associated documents is public and does not require an account. Some Georgia events direct documents and responses to an external "Event Link" (Team Georgia Marketplace); otherwise, submit your response as directed on the posting before the deadline.
Practical tips for preparing your response
Given this is a Best Value selection, focus on demonstrating not just your ability to meet the requirements, but also how your firm offers the most advantageous solution to the Georgia DOT. Highlight your experience with similar bridge replacement projects, especially those involving complex site conditions like active railroad tracks and trails.
Clearly articulate your proposed approach to both preconstruction and construction phases. Emphasize your understanding of current design standards and your ability to accommodate future infrastructure needs, such as the proposed track expansion. Provide specific examples of how your team has successfully managed projects of this scope and complexity, delivering on time and within budget.
See the live bid — deadline, agency details, and how to respond
Dates and requirements can change via addenda; always verify on the bid page and at the original source before responding.
View this bid on BiddingSimpleThis guide was prepared by BiddingSimple from the solicitation’s public posting. It is not official guidance from Department of Transportation-2; the original posting controls.