What the agency is buying

The U.S. Army Corps of Engineers, Omaha District, is seeking a small business contractor to design and install a zebra mussel mitigation system for the Gavins Point powerhouse raw water intakes in Crofton, Nebraska.

The project involves installing two local tank skids with spill containment, two pump skids for distribution, providing power to the pumps and ancillary equipment, and connecting the distribution pumps to existing raw water flow meters. This is a construction opportunity with an estimated value between $250,000 and $500,000.

Key dates and deadlines

The solicitation was published on July 29, 2026. An important site visit is scheduled for August 5, 2026. The deadline for submitting bids is August 31, 2026, at 3:00 PM ET. The contractor will need to start work upon receiving the contract award and complete the project within 210 calendar days after receiving the Notice to Proceed.

Who this opportunity suits

This opportunity is specifically restricted to small businesses. The primary NAICS code is 237110, Water and Sewer Line and Related Structures Construction, which has a small business size standard of $45 million. Firms with experience in water infrastructure, piping, pump systems, and related construction for industrial or power generation facilities are well-suited for this bid.

How to respond

To access the solicitation, click the “View original source” link. If the first click takes you to the portal’s homepage, click it again to go directly to the bid. You may need to create a free account on the portal to view all documents, though this is not always required. All questions regarding this solicitation must be submitted through ProjNet; access details and guidance are provided within the solicitation documents.

Practical tips for a competitive response

Given the technical nature of this project, ensure your proposal clearly demonstrates your firm's expertise in designing and installing specialized water treatment or mitigation systems. Highlight any past experience with similar projects involving pump skids, tank installations, and integration with existing facility infrastructure.

Attending the site visit on August 5, 2026, is highly recommended. This will provide crucial insights into the existing conditions at Gavins Point and allow you to ask clarifying questions directly, which can significantly strengthen your proposal. Pay close attention to the requirements for interfacing with existing flow meters and power supplies, as these details are critical for a successful installation.

See the live bid — deadline, agency details, and how to respond

Dates and requirements can change via addenda; always verify on the bid page and at the original source before responding.

View this bid on BiddingSimple

This guide was prepared by BiddingSimple from the solicitation’s public posting. It is not official guidance from DEPT of Defense; the original posting controls.