How to bid on SR 18 bridge work for the Pennsylvania Department of Transportation

Pennsylvania Department of Transportation New Brighton, PACloses December 17, 2026

What PennDOT is buying

PennDOT is seeking a prequalified contractor to preserve two multi-span bridges on SR 18 over the Beaver River in Beaver County. Work includes deck overlays, joint replacement, concrete repairs, painting, and other construction across about 2,500 feet.

The estimated project cost is $10 million to $12.5 million. For bridge contractors with the required PennDOT prequalification, this is a substantial bridge preservation project. The work must be completed by September 28, 2028.

Deadline and bid opening

Bids are due electronically through ECMS by December 17, 2026, at 11:00 a.m. Eastern. PennDOT opens bids at its letting at that time.

The public bid opening is at the Commonwealth Keystone Building, 7th Floor, Contract Awards Room, 400 North Street, Harrisburg. Visitors should allow time to obtain a pass on the 5th Floor and be escorted to the 7th Floor.

Who this opportunity suits

This opportunity is for bridge construction contractors that are prequalified with PennDOT and have an ECMS business partner account. The work centers on preservation of two bridges, including concrete, deck, joint, and painting work.

The project is in New Brighton Borough and the City of Beaver Falls, in Beaver County. The listed DBE goal is 0%.

How to access and submit a bid

Select “View the original posting” to open the bid package in PennDOT’s ECMS. If ECMS opens to its home page, enter as a guest and open the posting again, or choose Search, then Bid Packages, and search for project 105441.

The ECMS package contains the plans, special provisions, bid items, addenda, and questions and answers. Addenda are posted electronically. Bidding requires PennDOT prequalification and an ECMS business partner account; submit the bid electronically through ECMS before the letting time.

Prepare a careful bridge-work response

Review the plans, special provisions, bid items, and every posted addendum and question-and-answer entry. Check that your pricing and proposed work account for the listed bridge preservation tasks and project limits.

Confirm your prequalification and ECMS business partner access well before the deadline. Allow time to complete the electronic submission and verify that it has been submitted before 11:00 a.m. Eastern.

See the live bid — deadline, agency details, and how to respond

Dates and requirements can change via addenda; always verify on the bid page and at the original source before responding.

View this bid on BiddingSimple